NOTICE OF THE MAKING OF A COMPULSORY PURCHASE ORDER UNDER AND FOR THE PURPOSES OF SECTION 76 OF AND THE THIRD SCHEDULE TO THE HOUSING ACT, 1966, AS AMENDED BY SECTION 198 OF THE RESIDENTIAL TENANCIES ACT 2004, AS EXTENDED BY SECTION 10 OF THE LOCAL GOVERNMENT (NO.2) ACT, 1960 SUBSTITUTED BY SECTION 86 OF THE HOUSING ACT, 1966, AS AMENDED BY SECTION 6 AND THE SECOND SCHEDULE TO THE ROADS ACT, 1993 AND AS AMENDED AND EXTENDED BY: THE PLANNING AND DEVELOPMENT ACTS, 2000-2021 (INCLUDING PART XIV, SECTION 213, SECTION 213(2) AND SECTION 222 THEREOF); LOCAL GOVERNMENT ACTS 1925-2019 INCLUDING SECTIONS 11 AND 184 OF THE LOCAL GOVERNMENT ACT, 2001; ROADS ACTS 1993-2015 AND PART XIV OF THE PLANNING AND DEVELOPMENT ACT, 2000 AND ALL OTHER ACTS, THEREBY ENABLING PUBLICATION  IN ACCORDANCE WITH ARTICLE 4(A) OF THE THIRD SCHEDULE TO THE HOUSING ACT, 1966 AS AMENDED.

  

COMPULSORY ACQUISITION OF LAND

CORK CITY COUNCIL – LISHEENS, BALLINCOLLIG, ACQUISITION

 ORDER NO.4 OF 2022

(Click on map for larger PDF image)

Lisheens-image

Lisheens-CPO-map.pdf (size 4.2 MB)

Lisheens-CPO-Schedule.pdf (size 264 KB)

Cork City Council (hereinafter referred to as “the local authority”) in exercise of the provisions of section 76 of the Housing Act,1966 and the third Schedule thereto, as amended by section 198 of the Residential Tenancies Act 2004, as extended by section 10 of the Local Government (No.2) Act, 1960 substituted by section 86 of the Housing Act, 1966, as amended by section 6 and the second Schedule to the Roads Act, 1993 and as amended and extended by The Planning and Development Acts, 2000-2021(including Part XIV, Section 213, Section 213(2) and Section 222 thereof); Local Government Acts 1925-2019 including sections 11 and 184 of the Local Government Act, 2001; Roads Acts 1993-2015 and Part XIV of the Planning and Development Act, 2000 and all other Acts, has made an order entitled as above which is about to be submitted to An Bord Pleanala for confirmation. If confirmed, the order will authorise the local authority to acquire compulsorily the lands described in the Schedule Part 1 and Part 11 hereto together with any easement, wayleave, water- right or other right over or in respect of the said lands or water or any sub-stratum of the said lands for the purposes of performing its functions under the Planning and Development Act, 2000 including giving effect to and facilitating the implementation of the City Development Plan.  

 

Owners, lessees and occupiers of the lands described in the Schedule Part 1 and Part 11, will receive individual written notice.

 

The Board cannot confirm –

 

a compulsory purchase order in respect of the land if an objection is made in respect of the acquisition by an owner, lessee or occupier of the land and not withdrawn, until it has caused to be held an oral hearing into the matter and until it has considered the objection and the report of the person who has held the oral hearing.

 

 

A copy of the order and of the map referred to in it may be seen between the hours of 9am to 5pm on working days between the 26th of August 2022 and the 14th of October 2022 at the reception desk, City Hall.   

 

 

SCHEDULE

 

PART 1

 

The lands to which the Order relates are described as follows: -

  

Schedule Number 1

 

Starting at a point on the southern boundary of the R608 approximately 279.5 metres west of the north western corner of the Lisheen Woods residential development, thence following a southerly line for approximately 20.5 metres along the boundary of an uninhabitable residential property, thence following a south westerly line for approximately 57.5 metres along the rear boundary of said property to meet the boundary of the entrance avenue to residential property at Lisheens, thence following a north westerly line for approximately 19.5 metres along the boundary of said property to where it meets the R608 and returning to the starting point following a line along the boundary of said property with the R608 for approximately 60.5 metres.

  

 PART II

 

Schedule Number 2

 

Starting at a point on the southern boundary of the R608 approximately 222 metres west of the northwestern corner of Lisheen Woods residential development, thence following a south easterly line through lands at Lisheens for approximately 111 metres, thence following a north easterly line through lands at Lisheens for approximately 125 metres, thence following a south easterly line through lands at Lisheens for approximately 166 metres, thence following a south westerly line through lands at Lisheens for approximately 60 metres, thence following a westerly line along the northern boundary of the N22 for approximately 354 metres, thence following a north westerly line for approximately 57 metres to the south western corner of residential property at Lisheens, thence following a north easterly line for approximately 88 metres along the southern boundaries of residential property at Lisheens, thence following a north westerly line for 5 metres along the southern boundary of a residential property at Lisheens, thence following a north easterly line for approximately 45 metres along the southern boundary of residential property at Lisheens, thence following a north westerly line for approximately 72.5 metres along the eastern boundary of residential property at Lisheens, thence following a north easterly line for approximately 57.5 metres along the rear boundary of an uninhabitable property at Lisheens, thence following a north westerly line for approximately 20.5 metres along the boundary of said property to the R608 and returning to the starting point following a line in an easterly direction for 57.5 metres along the boundary of the R608

 

Dated this 26th day of August 2022